Natural Gas's Share of the Planned Power Pipeline

By Dror Poleg

This chart follows natural gas's share of the planned U.S. power pipeline through each monthly EIA generator inventory. One line covers every planned generator; the other covers only those whose construction has started. Batteries are left out because storage does not generate energy. When the first line sits above the second, gas makes up more of what is still being planned than of what is being built.

Latest observation: 2026-09·Expected cadence: Monthly
EnergyClimateBusiness
What does it show?

Natural gas rose from 24.0% to 31.5% of planned U.S. generating capacity between the January 2026 and September 2026 EIA inventories (48 to 71 GW), but among projects whose construction has started its share moved only from 15.2% to 17.6%.

Methodology

Each point is one monthly EIA-860M inventory, dated to the month it describes. Reads the Planned sheet, excludes rows whose status is Operating, keeps every other published status, and sums nameplate capacity in MW. Natural gas is every technology whose EIA name begins Natural Gas (combined cycle, combustion turbine, internal combustion engine, steam turbine). The first line divides gas MW by all planned generating MW; the second does the same for generators whose construction has started or finished but which are not yet in commercial operation (EIA statuses U, V and TS). Battery storage (discharge MW) and the few storage rows EIA leaves without a technology label are excluded from both denominators, matching the generation totals in the dashboard's planned power pipeline chart. Gas at the earliest stage, planned with regulatory approvals not yet initiated: 20.8 GW in January 2026, 39.7 GW in September 2026. The largest gas plant in the September 2026 inventory, Project Matador Gas Plant (PMG) in TX (11.7 GW, first listed in March 2026), weighs heavily: without it gas would be 27.8% of planned generating capacity. Limitations: shares are of nameplate capacity, not of the electricity the plants would generate. Planned capacity is not a forecast of what will be built, and the mix changes both when projects enter and when they leave the list by starting operation or being canceled or postponed. The inventory covers plants of at least 1 MW and excludes many behind-the-meter systems and unreported projects. It does not identify which projects serve data centers. Monthly EIA-860M figures are preliminary and revised. The series begins in January 2026; earlier vintages exist in EIA's archive.

Sources